SpaceMiningData
SpacecraftMoonIn development

Griffin Mission One (Griffin-1, NASA Moon Base II)

First flight of Astrobotic's Griffin lander (Astrobotic now operates as Voyager Lunar Systems), a NASA CLPS delivery to the lunar south pole with NASA's late-2026 target and Voyager's no-earlier-than-November-2026 bound (NASA names the Nobile Crater area; Voyager's 22 October 2026 article says near Mons Mouton). After NASA ended VIPER in 2024, its resource-relevant cargo is the NASA Ames/Interlune METAL investigation, which NASA says will study helium-3 abundance in the regolith.

Objective. Deliver NASA payloads including the METAL investigation (NASA Ames with Interlune), which NASA says will study helium-3 abundance in the lunar regolith to inform in-situ resource utilization.

Targeted

See the south pole on the 3D Moon

What to watch for

From the records here, checked 2026-10-28. Planned dates often slip.

  • Launch. Voyager gives no earlier than November 2026 and NASA gives late 2026. Neither is a launch day, and the two have not been reconciled.
  • Landing. This is the Griffin lander's first flight, to the lunar south pole. NASA names the Nobile Crater area and Voyager says near Mons Mouton; whether those are the same area or a site change is not established.
  • The helium-3 question. Since NASA ended VIPER in 2024, this flight's resource-related cargo is the METAL camera from NASA Ames and Interlune. It is intended to image lunar soil to map titanium content and soil maturity, which Interlune and NASA use as proxies to estimate helium-3. Any helium-3 estimate would be derived from those proxies.
  • What would change here. Both records stand at Targeted for helium-3. A launch or a landing would not change that. Each stays at Targeted until reported evidence supports inferring or measuring helium-3 under the site's evidence steps. How the steps work
  • Still open. Interlune says METAL flies on Astrolab's FLIP rover. NASA's Griffin-1 section lists METAL without naming FLIP, so the mounting is company-stated.

Facts

Kind
Spacecraft
Mission type
Prospecting
Target
MoonNobile Crater region, lunar south pole (per NASA)South polar region, no point: Lunar south pole missions
Launch
Planned, no earlier than 2026-11
Announcement date not recorded. Record checked 2026-10-28.
Launch vehicle
SpaceX Falcon Heavy
Phase
In developmentScoped schedule review on 2026-11-01: Voyager's 13 July 2026 release targets launch no earlier than November 2026. NASA's 13 October testing report still gives late 2026, while Voyager's October report describes final preparations before shipment. The date field records the published earliest-month bound, not a confirmed November launch. No actual launch or fixed launch day is established, so the phase remains in development. Older NASA schedule and landing-site discrepancies remain open.
Outcome
Not applicable
Why it is included
Stated resource objective

How this launch date changed

Recorded change: the plan before → the plan after, oldest first.

  1. 2026-05-26: no earlier than fall 2025 → late 2026 (2026-H2 target)Schedule slip [3]
  2. 2026-11-01: late 2026 (2026-H2 target) → no earlier than November 2026 (2026-11 net)Source update [13]
Current launch date: Planned, no earlier than 2026-11
Griffin Mission One (Griffin-1, NASA Moon Base II): launch dates on record2026-05-26: no earlier than fall 2025 → late 2026 (2026-H2 target). 2026-11-01: late 2026 (2026-H2 target) → no earlier than November 2026 (2026-11 net).Apr 2026Jul 2026Oct 202620252026Date of the recorded changePlanned launch dateno earlier than November 2026…
Each band is a plan as recorded between recorded changes; it may have changed in between without a record. The coloured band is the newest plan. A dashed edge means the plan began earlier than shown. An arrow on top means no earlier than. A band can be wider than the words it stands for; the list gives them exactly.

Only changes recorded here are listed. The oldest date shown may not be the first plan ever announced, and a date with no recorded change may still have moved. A plan is not a launch.

All recorded schedule changes

What comes next

Next recorded dates are plans, not results.

Launch: Planned, no earlier than 2026-11Announcement date not recorded. Record checked 2026-10-28.

Participants

Operators, payload owners, carriers and customers are recorded separately.

Carried on this mission

Resources and evidence

ResourceEvidence
Helium-3Targeted

Open evidence gaps

  • Interlune's 15 September 2026 blog says the company funded METAL's flight on Astrolab's FLIP rover; NASA's Moon Base Phases page lists METAL among Griffin-1 payloads and does not name FLIP in that section. The mounting on FLIP is therefore company-stated, not confirmed by the reviewed NASA section.
  • Voyager's no-earlier-than-November-2026 statement is an earliest-month bound, not confirmation of a November launch or an exact day. NASA's October report says late 2026; older NASA pages retain earlier schedules. Their reconciliation and the actual launch day remain unresolved.
  • Landing-site naming differs: NASA's Griffin-1 pages (October 2026) say Nobile Crater, while Voyager's 2026-10-22 article says near Mons Mouton. Whether these describe the same area or a site change is not established.

Record history

changes to this record's facts, newest first

ChangedFieldWasNowReasonSource
2026-11-10open evidence gapsWhether METAL is mounted on Astrolab's FLIP rover (Interlune/Astrolab 2025 release) or on the lander deck; msn-interlune-metal-camera points here directly, skipping FLIP.Interlune's 15 September 2026 blog says the company funded METAL's flight on Astrolab's FLIP rover; NASA's Moon Base Phases page lists METAL among Griffin-1 payloads and does not name FLIP in that section. The mounting on FLIP is therefore company-stated, not confirmed by the reviewed NASA section.Correction[16]
2026-11-01launch datelate 2026 (2026-H2 target)no earlier than November 2026 (2026-11 net)Source update[13]
2026-10-31open evidence gapsNo launch month or day is published; NASA and Voyager give only late 2026.Voyager targets launch no earlier than November 2026 (13 July 2026 release); the exact launch day and reconciliation of the conflicting schedule statements remain unresolved.Correction[12]
2026-05-26launch dateno earlier than fall 2025late 2026 (2026-H2 target)Schedule slip[3]
2024-07-17objectiveDeliver NASA's VIPER water-ice prospecting rover (2020 CLPS award)Griffin flight demonstration without VIPERReclassification[5]

Sources

16 excerpts from 10 publications

One web address counts as one publication.

  1. NASAGovernment recordPublished 2026-05-26Accessed 2026-10-28Supports: phase, launch date
    The lander is being prepared for transport to NASA's Jet Propulsion Laboratory, where it will undergo environmental testing ahead of its planned launch to the Moon in late 2026.
    Quote matched the source text when accessed.
  2. NASAGovernment recordPublished 2026-05-26Accessed 2026-10-28Supports: why it is included, objective, resources, participants
    the Moon Exploration for Titanium with Active Lighting (METAL) investigation, developed by NASA's Ames Research Center in partnership with Interlune. METAL will study the abundance of helium-3 in the lunar regolith
    Quote matched the source text when accessed.
  3. NASAGovernment recordPublished 2026-05-26Accessed 2026-10-28Supports: participants, record history
    Moon Base II: Planned for launch later this year, this mission will deliver more than 1,100 pounds of cargo on Astrobotic's Griffin lander, including Astrolab's FLIP rover
    Quote matched the source text when accessed.
  4. NASAGovernment recordAccessed 2026-10-28Supports: summary, target site
    The Astrobotic Griffin-1 mission will deliver more than 1,100 pounds of cargo to the Nobile Crater at the lunar South Pole, including the Astrolab FLIP rover
    Quote matched the source text when accessed.
  5. NASAGovernment recordPublished 2024-07-17Accessed 2026-10-28Supports: record history
    Astrobotic will continue its Griffin Mission One within its contract with NASA, working toward a launch scheduled for no earlier than fall 2025. The landing without VIPER will provide a flight demonstration of the Griffin lander and its engines.
    Quote matched the source text when accessed.
  6. Voyager TechnologiesCompany statementPublished 2026-07-13Accessed 2026-10-28Supports: participants, summary
    Astrobotic now operates as Voyager Lunar Systems
    Quote matched the source text when accessed.
  7. AstroboticCompany statementPublished 2021-04-13Accessed 2026-10-28Supports: open evidence gaps
    SpaceX’s Falcon Heavy completes our Griffin Mission 1 (GM1) solution by providing a proven launch vehicle to carry us on our trajectory to the Moon.
    Quote matched the source text when accessed.
  8. NASA ScienceGovernment recordPublished 2026-10-13Accessed 2026-10-28Supports: launch date, launch vehicle
    Griffin-1 is expected to launch in late 2026 aboard a SpaceX Falcon Heavy rocket.
    Quote matched the source text when accessed.
  9. Voyager TechnologiesCompany statementPublished 2026-10-13Accessed 2026-10-28Supports: phase
    Griffin-1 is now returning to Voyager’s Lunar Systems headquarters in Pittsburgh, where the team will complete final preparations ahead of shipment to Cape Canaveral, Florida for launch.
    Quote matched the source text when accessed.
  10. Voyager TechnologiesCompany statementPublished 2026-10-22Accessed 2026-10-28Supports: launch date
    expected to launch with 10 payloads in late 2026
    Quote matched the source text when accessed.
  11. Voyager TechnologiesCompany statementPublished 2026-10-22Accessed 2026-10-28Supports: open evidence gaps, summary
    Our team has been diligently running repeated landing simulations to give us the highest assurance of a safe and precise landing near Mons Mouton at the South Pole.
    Quote matched the source text when accessed.
  12. Voyager TechnologiesCompany statementPublished 2026-07-13Accessed 2026-10-31Supports: open evidence gaps, record history
    Launch is targeted no earlier than November 2026.
    Quote matched the source text when accessed.
  13. Voyager TechnologiesCompany statementPublished 2026-07-13Accessed 2026-11-01Supports: launch date, status explanation, record history
    Launch is targeted no earlier than November 2026.
    Quote matched the source text when accessed.
  14. NASA ScienceGovernment recordPublished 2026-10-13Accessed 2026-11-01Supports: status explanation, open evidence gaps
    Griffin-1 is expected to launch in late 2026 aboard a SpaceX Falcon Heavy rocket.
    Quote matched the source text when accessed.
  15. Voyager TechnologiesCompany statementPublished 2026-10-13Accessed 2026-11-01Supports: phase, status explanation
    Griffin-1 is now returning to Voyager’s Lunar Systems headquarters in Pittsburgh, where the team will complete final preparations ahead of shipment to Cape Canaveral, Florida for launch.
    Quote matched the source text when accessed.
  16. InterluneCompany statementPublished 2026-09-15Accessed 2026-11-10Supports: open evidence gaps
    Interlune obtained the Moon Exploration for Titanium with Active Lighting (METAL) instrument from the Ames Research Center and funded its flight to the Moon on Astrolab’s FLIP rover.
    Quote matched the source text when accessed.

Cite this record

SpaceMiningData, “Griffin Mission One (Griffin-1, NASA Moon Base II)”, dataset version a00fa2c68a45, built 2026-11-11, https://spaceminingdata.com/missions/astrobotic-griffin-1.html. Record checked 2026-10-28.